Trading Details
Resource Development Foundation (RDF) initially started infrastructure development projects besides its social development activities Jointly with the Cardinal Group from September 28, 2020 through implementation of Naogaon Haor Project at Mithamoin under Kishoregonj district (Block making for slope protection work of submersible embankment) financial supported by Bangladesh Water Development Board (BWDB). Later on, RDF has been made a significant contribution in the infrastructure development sector of the country through implementing several such types of projects.
RDF has earned the reputation of one of the leading construction/infrastructure sector of the country, capable to undertake any kind of infrastructure development projects which require specialized professional experience with requisite technical knowledge.
RDF has the specialization and experience with required in-house logistic facilities to undertake any kinds of traditional or turnkey projects observing all types of procurement methods as preferred by the clients. The diversity of the projects completed has been very critical which has helped RDF to attain present success & status. RDF’s portfolio of projects includes all sectors of the construction industry both in the private & public sectors. RDF has so far completed various multidiscipline projects since its inception. These are very rare achievements in the history of the construction industry in Haor areas of Bangladesh.
Quality & efficiency is the vision & philosophy of this organization. RDF follows international standards along with national standards prevailing in the country in all respect. Quality of works is ensured at every stage of works by professional Engineers & professionals.
SL |
Name of the Projects |
Project Location |
Budget |
Project Duration |
Financed by |
01 |
Slope protection work of submersible embankment around Naogaon Haor sub project |
Mithamoin, Kishoregonj District. |
14, 83, 79,089 |
20.01.2021 to 14.12.2022 |
Bangladesh Water Development Board (BWDB) |
02 |
Construction of flood wall along the bank protection project |
Moulvibazar District |
36,62,03,286.55 |
20.04.2021 to 30.11.2022 |
Bangladesh Water Development Board (BWDB) |
03 |
Bank protection work along the right bank of the Jamuna river |
Gaibandha Sadar & Sundargonj Upazila, Gaibandha District |
11,09,86,944 |
23.02.2021 to 26.06.2022 |
Bangladesh Water Development Board (BWDB) |
04 |
Bank protection work along the right bank of the Jamuna river |
Shaghata Upila, Gaibandha District |
21,83,71,210 |
15.07.2021 to 30.04.2023 |
Bangladesh Water Development Board (BWDB) |